공사대금등
1. The Plaintiff:
A. Defendant A Co., Ltd.: (a) KRW 99,197,250; and (b) from January 13, 2012 to May 8, 2012.
1. Claim against Defendant A corporation
A. Although the Plaintiff’s indication of the claim completed all of the construction works under the contract for the Chang Metal Works (the increased construction cost) and the contract for the Chang Metal Work (the increased construction cost) among the multi-household multi-household multi-household housing construction (the construction cost of KRW 209,00,000) that was entered into on August 17, 201 with Defendant A Co., Ltd. (hereinafter “Defendant A”), Defendant A did not pay the total construction cost of KRW 99,197,250,00 among the above construction cost, on the ground that the Defendant A did not pay the total construction cost of KRW 99,197,250,00 among the above construction cost.
Article 208 (3) 1 of the Civil Procedure Act)
2. Claims for the housing construction of Defendant B, stock company, etc.
A. On August 1, 2011, the Plaintiff entered into a contract for the Chang Metal Works (the construction cost of KRW 33,000,000 (the increase in the construction cost of KRW 35,197,250) and the construction period from August 6, 201 to October 6, 201) with the Defendant during the extension of the D Hospital located in Seongdong-gun D Hospital, and completed the construction under the said contract. However, the Defendant A paid the down payment of KRW 5,00,000,000, the remainder of the construction cost of KRW 30,197,250 after paying the down payment of KRW 5,00.
B) On August 17, 2011, the Plaintiff is a multi-household housing corporation E and F ground (hereinafter “instant loan”) with Defendant A in Ansan-si, Dong-si.
(2) Of the contract for Chang Metal Construction (total construction cost of KRW 209,00,000, and construction period of KRW 209,000,000; and between August 24, 201 and October 31, 201; hereinafter referred to as “instant contract”).
(2) Defendant B’s joint and several sureties’s joint and several sureties’s joint and several sureties’s payment of KRW 69,000,000 for the remainder of the construction cost after the payment of KRW 140,000,00 for the down payment, etc. was made. Defendant A’s payment of KRW 59,000 for the construction cost that Defendant A owes to the Plaintiff under the instant contract.