(영문) 부산지방법원 2014.12.23 2014가단79699

대여금

Text

1. The defendant shall pay to the plaintiff the amount of KRW 156,845,659 and the amount of KRW 74,818,664 from July 18, 2014 to the date of full payment.

Reasons

The plaintiff is deemed to have led to confession pursuant to Article 150 (1) of the Civil Procedure Act because the defendant does not clearly dispute the payment of the money stated in the order as the grounds for the application (However, the creditor is deemed to be the defendant) in the same manner as the reasons for the application.

Therefore, the Defendant is obligated to pay to the Plaintiff damages for delay calculated at the rate of 18% per annum, which is the rate of delay damages from July 18, 2014 to the date of full payment of the principal and interest of interest of KRW 156,845,659 and the balance of loans of KRW 74,818,664.

Therefore, the plaintiff's claim of this case is reasonable, and it is decided as per Disposition.