(영문) 부산지방법원 2020.08.19 2017가합52593

손해배상(기)

Text

The plaintiff's claim against the defendants is dismissed in entirety.

Litigation costs shall be borne by the plaintiff.

Reasons

1. Basic facts

A. The Plaintiff is a company that is engaged in the development, development, transmission, distribution of electricity resources, and business related thereto, and is engaged in the development, distribution, and distribution of electricity resources, and an urban development project of Ulsan-gu Seoul Special Metropolitan City (hereinafter “D Zone Urban Development Project”) is the instant project.

b)the installation of the power distribution pipe in the site (hereinafter referred to as “instant construction”);

(2) The construction supervision services for the project owner and the contractor (hereinafter referred to as “instant construction supervision”).

2) Defendant A Co., Ltd. (hereinafter “Defendant A”) is a company engaging in electrical construction business, etc. and is the contractor of the instant construction business.

3) Defendant B Co., Ltd. (hereinafter “Defendant B”).

(B) The Plaintiff is a supervisor of the instant construction project, who is engaged in the construction, electricity, design services, supervision services, etc. Around June 201, the Plaintiff is a facility that connects electricity from electric facilities installed outside the instant project district to the instant project district for the purpose of supplying electricity within the project site with the D Zone Urban Development Project Association (hereinafter referred to as the “D Zone Association”) around June 201.

(hereinafter referred to as “instant power distribution pipe”) concluded a performance agreement which includes the establishment of the power distribution pipe and the receipt of the construction cost actually required.

2) On February 8, 2013, the Plaintiff entered into a contract for construction works with Defendant A and the instant construction works with the terms of KRW 1,544,70,000 as to the contract amount, March 11, 2013 as of the commencement date, and January 4, 2014 as of the completion date (hereinafter “instant construction contract”).

B. On December 26, 2013, the instant contract was concluded to extend the completion date of the instant construction to May 31, 2014, respectively, and the contract was concluded to increase the contract amount to KRW 1,895,449,235 on April 3, 2014.

3.10 Pipe works; 3.10.1

(a) 1) In the case of an installation depending on the roads laid underground, the center line of the underground cable lines and the center line of the roads shall be installed to avoid the center of the roads as much as possible;

3.If possible.