(영문) 대구지방법원안동지원 2017.10.26 2017가합3045
채무부존재확인
Text

1. It is confirmed that each obligation listed in the separate sheet No. 1 list against the plaintiffs against the defendant does not exist.

2...

Reasons

1. Basic facts

A. The Defendant’s plan to create the Saemaul Movement Gu Park Gu, 1) from March 201 to March 1, 201, was established with a size of 245,697 square meters located in the members of the Gu-U.S. Si, Si, Gu, which had a birth of the former president C for the purpose of re-helping the Saemaul Movement. The Defendant is a Saemaul Movement Gu park (hereinafter “instant facility”).

) A project to create a project (hereinafter referred to as “instant project”);

On November 23, 2011, an industry-academic cooperation foundation of the Daegu University entered into a service contract with the Administrator of the Cultural Heritage Administration to conduct an on-site surface inspection of the instant cultural heritage site. Under Article 6(1) of the Act on the Protection and Inspection of Buried Cultural Heritage, the implementer of construction works above a certain scale must conduct an on-site surface inspection in advance to verify whether cultural heritage is buried and distributed in the relevant construction area. (2) An industry-academic cooperation foundation of the Daegu University has designated the Central Museum of the Daegu University as an on-site inspection agency to conduct an on-site inspection of cultural heritage in the instant site from November 28, 201 to February 25, 2012, submitted an on-site inspection report of the cultural heritage surface inspection to the Defendant, and around that time, the Defendant submitted the said report to the Administrator of the Cultural Heritage Administration, stating the above report on the on-site inspection of the cultural heritage surface in the instant site in order to verify whether the cultural heritage was buried and distributed in the relevant construction area.

3) In relation to the instant business, the Defendant is entitled to the National Land Planning and Utilization Act (hereinafter “National Land Planning Act”).

(2) The Act on the Management of Urban Parks, Greenbelts, Etc. (hereinafter referred to as the “Act on the Management of Parks and Greenbelts”)

In order to formulate a park building plan according to the plan.