1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

Basic Facts

A. The Plaintiff is a company established in the Hong Kong Special Administrative Region in Hong Kong, which is engaged in the business of manufacturing Pium 3 blades.

On the other hand, the defendant is a domestic company with the purpose of exporting and importing industrial machinery.

B. On March 10, 2011, the Plaintiff entered into an agreement with the Defendant on the promotion of the project for the construction of a manufacturing plant of the Insium 3 bladesium (hereinafter “instant agreement”) with the Plaintiff (hereinafter “instant project”). The main contents are as follows.

Article 2 (Duties of “A” (hereinafter the same shall apply) A (referring to “Plaintiffs”; hereinafter the same shall apply) shall submit to “B” (hereinafter the same shall apply) the following materials within 60 days after the conclusion of this Agreement:

2-1. Business Plan (Form Two copies in English or Korean), 2-2. Business Registration Certificate (Korean) 2-3. Various design drawings and related data (based on design drawings owned by A) 2-4. Environmental impact assessment report (data issued by the competent agency of the factory) 2-5. Other documents deemed necessary for the implementation of the business and requested by B (hereinafter referred to as “A”), Article 3(2) of the documents (hereinafter referred to as “the documents”) to be submitted to A within 30 days after receipt of the documents specified in Article 2 by A:

(A) The 3-1. Plan for the Implementation of the Fund for Facilities 3-2. The 3-3-4. Statement of Investment in Facilities 3-5. The 3-6. Preparation of the 3-6. Plan for the Purchase of Facilities (Supply) by Equipment 3-5. The 3-6. Preparation of the 3-6. Plan for the Submission of Financial Rights 3-6. After completion of the work under Articles 2 and 3, the work will proceed in accordance with the following procedures:

4-1. When the duties of Gap and Eul are completed pursuant to Articles 2 and 3, "a contract for facility purchase (supply)" between Gap and Eul shall be concluded, and the total amount of the contract shall be approximately five billion won.

4-2. Within 10 days after concluding a “facility purchase contract”, A shall pay 15% of the total amount of the contract to B as the down payment, and B.