Text
1. The defendant shall pay to the plaintiff the amount of KRW 39,40,058 and KRW 33,933,889 among them, from November 30, 2019 to the day of full payment.
Reasons
On October 24, 2017, the Plaintiff and the Defendant entered into a long-term siren contract (hereinafter “instant contract”) to be used by the Defendant (hereinafter “instant contract”) at the rate of 45,58,098 won, 826,100 won per annum, 60 months of the contract period, and 25% per annum of 25% of the amount used by the Defendant during the period of contract. The Defendant lost its profits due to the Defendant’s failure to pay rental fees from December 17, 2018. The principal amount the Defendant failed to pay by November 29, 2019 was 3,93,83,89 won, interest and compensation for delay was 5,46,169 won, or there was no dispute between the parties, or it can be acknowledged in accordance with the purport of the entire pleadings and arguments as stated in Gap evidence 1 through 5.
According to the above facts, the Defendant is obligated to pay to the Plaintiff the interest and damages for delay up to November 29, 2019, the amount of KRW 33,400,058 (= Principal KRW 33,93,889, KRW 5,466,169) and KRW 33,93,89, whichever is applicable, to the Plaintiff at the rate of 24% per annum from November 30, 2019 to the date of full payment.
Therefore, the plaintiff's claim of this case is justified and it is so decided as per Disposition by the assent of all.