(영문) 수원지방법원평택지원 2016.11.09 2016가합8383
손해배상(기)
Text

1. The Defendant (Counterclaim Plaintiff) paid KRW 91,051,454 to the Plaintiff (Counterclaim Defendant) and its amount from October 30, 2015 to November 9, 2016.

Reasons

The main lawsuit and counterclaim shall be examined together.

Basic Facts

The plaintiff is a corporation with the objective of manufacturing and selling steel products, and the defendant is a corporation with the purpose of manufacturing, assembling, and installing steel products.

On October 15, 2014, the Plaintiff entered into a contract for construction works between the Plaintiff and the Defendant with respect to high fire-making and crushing storage works among the new construction works of racing factories that were contracted by the Daeho Industrial Development Co., Ltd. (hereinafter referred to as the “Moho Industrial Development”), and the parts related to the instant case in the terms of the contract are as follows.

Since then, the Plaintiff and the Defendant changed the construction cost into KRW 1,613,026,902 (excluding value-added tax) by having the Plaintiff directly perform the construction work for a silo which was included in the original contract scope.

(1) The term “this case’s construction project” and “this case’s contract”). Article 1 (Scope of Construction Works: 1) High fire manufacturing and mixed crushing storage Work: The scope of construction Works: 2.0 million won for high fire: 1HR/180TN; 2) the time limit limit limit of storage facilities (3,000 tons for 1HR/20 TUN: 3,000 tons for 2,50 square meters: