(영문) 서울중앙지방법원 2017.08.29 2015가단5289261

구상금

Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Facts of recognition;

A. The Plaintiff is an insurance company that entered into a comprehensive automobile insurance contract with A and B (hereinafter “Plaintiff”) and the Defendant is a road manager at the location where the following traffic accidents occur, who is installed and managed signal apparatus installed in the above part of the road.

B. At around 00:50 on May 2, 2014, Dong C operated the Plaintiff’s vehicle and operated the front road along the intersection of the 176-4 square street in Gangseo-gu, Gangseo-gu, Seoul, through a four-lane radius from the side of the side of the side of the side of the road to the side of the office of Gangseo-gu. At the said intersection, the vehicle signal at the said intersection was red signal, but entered the said intersection in violation of the signal. Pursuant to the Madle Sar New, the above intersection was in conflict with the front part of the D driver’s vehicle running the said intersection as a erobbbr (hereinafter referred to as “road vehicle”) and the left part of the Plaintiff’s vehicle, and due to the collision of other vehicles with the signal signal atmosphere, the latter collisioned with the latter.

C. D, who was aboard the Plaintiff’s vehicle due to the foregoing traffic accident (hereinafter “instant accident”), the F, G, H, and I suffered respective injuries from the other vehicles, and the J, which was aboard the Plaintiff’s vehicle, died, and the Plaintiff’s vehicle and the other party’s vehicle were totaled destroyed 6 costs of the vehicle.

Meanwhile, in the intersection where the instant accident occurred, one street apparatus (hereinafter “third signal apparatus”) was installed at the end of the intersection prior to the entrance into the intersection, one street apparatus (hereinafter “second signal apparatus”) at the end of the intersection, and at a point of approximately 20 meters right after the intersection, and one street apparatus (hereinafter “third signal apparatus”) at the end of the intersection. Among them, the first signal apparatus and the second signal apparatus are signal apparatus for vehicles intending to enter the intersection.