beta
(영문) 수원지방법원 2014.09.05 2013가합4206

손해배상(기)

Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. On November 15, 201, the Plaintiff asserted that the construction work should be subcontracted to KRW 115,00,00 among the construction works for new and multi-households and 200,000. The above contract should not be delayed (including negligence) or suspended for any reason. If the construction work is delayed for 2 weeks or more, the subcontractor shall waive the construction work, and if the construction work is delayed for 15 weeks or more, the construction work cost should be paid between the contractor and sub-subcontracts by type of work to which the subcontractor belongs, and the amount of compensation for 00,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,000,00,000.).